Honest Echo
Honest EchoKnow Before You Bid
How it worksPricing
Sign inStart free
Honest Echo
Honest EchoKnow Before You Bid

Fairfax, VA

[email protected]

Product

  • How Pursuit Works
  • Free Analyzer
  • Pursuit Readout
  • Construction Contracts
  • OT & CSO Notices
  • Pricing
  • Security
  • FAQ

Who It’s For

  • Small Business Owners
  • Proposal Managers
  • GovCon Consultants

Company

  • About
  • Contact
  • Terms of Service
  • Privacy Policy

Compare

  • vs GovWin
  • vs GovTribe
  • SAM.gov Analysis

Guides

  • All Guides
  • FAR 2.0 Cheat Sheets
  • FAR Part 19 Changes
  • FAR Overhaul Tracker
  • Sources Sought Guide
  • Hidden Opportunities
  • Recompete Tracking

© 2026 Honest Echo LLC. All rights reserved.

Start Free →Sign In →
FAR Overhaul TrackerPart 19
FAR Part 19 · Small Business

Part 19, rewritten. What changed for small business.

The current rule and the rewrite, side by side, in plain English.

Model text: Sep 26, 2025, updated Feb 20, 2026Proposed rule: not yet publishedFinal rule: no date announced

Status verified Nov 16, 2026. Comparison written Nov 2, 2026 from acquisition.gov.

The short version

  1. 1Set-asides of orders under multiple-award contracts stay discretionary, and a decision not to set one aside can no longer be protested.
  2. 2The rule of two still governs contracts, but the FAR no longer tells contracting officers to consider 8(a), HUBZone, SDVOSB or WOSB programs first.
  3. 3Until a final rule takes effect, the rewrite reaches a contract only through an agency's class deviation and the clauses in that contract. The status line above shows where the formal rulemaking stands.

Is it in effect at my agency?

Department of Defense: class deviation 2026-O0037, Revision 1, in effect since Feb 1, 2026; current version dated Jul 24, 2026 (DoD's DFARS deviation list). Source

Until a final rule takes effect, the rewritten text applies only where an agency has adopted it by class deviation, and an awarded contract keeps its clauses until it is modified. As of Nov 2, 2026, the official FAR still showed the current Part 19 (2026-01).

What changed

17 changes that matter to small contractors, most consequential first. Section cites are in the text; every change links to both versions.

Set-asides of orders under multiple-award contracts

Narrowed

Current FAR

Order set-asides are discretionary, but the CO must state in the solicitation and contract whether order set-asides will be discretionary or mandatory when the rule of two is met; a mandatory version uses 52.219-13 Alternate I (FAR 19.504(a)(1), 19.507(f)(2)).

Rewritten Part 19

Order set-asides stay discretionary, and the CO's decision to set aside or not set aside an order is stated to be not a basis for protest; 52.219-13 Alternate I is marked [Reserved] (RFO 19.111-2(a); RFO 52.219-13).

What it means for you (our reading)

Where a vehicle carries the rewritten clause (a new award, or an existing contract modified to add it), a small business can't rely on language committing the agency to set aside qualifying orders, and challenging a decision not to set one aside gets much harder. Agency adoption alone doesn't change an awarded contract: check your vehicle's clauses and modifications. The FAR Companion says the wording is meant to settle a GAO vs. Court of Federal Claims split over the rule of two on multiple-award contracts.

Who it hits: Small business holders of multiple-award contracts (MAS, GWACs, IDIQs)Current FAR Current FAR Rewritten text Rewritten text acquisition.gov Practitioner Album SBA rule (eCFR)

Rule of two for contracts

Same Rule, New Words

Current FAR

Acquisitions above the micro-purchase threshold up to the SAT are automatically set aside for small business unless the CO lacks a reasonable expectation of two competitive small offerors; above the SAT the CO must set aside when that expectation exists (FAR 19.502-2(a)-(b)).

Rewritten Part 19

For contracts above the micro-purchase threshold, the CO must set the contract aside when there is a reasonable expectation of offers from two or more responsible, competitive small businesses, and must document a decision not to (RFO 19.104-1(a)-(b)). The word 'acquisition' became 'contract', and the Practitioner Album says the rule of two does not apply to orders.

What it means for you (our reading)

For standalone contracts the set-aside obligation is essentially the same; the FAR Council kept it above the SAT even though only the MPT-to-SAT band is statutory. The real change is the explicit carve-out of orders (see the order set-aside item).

Who it hits: All small businesses bidding standalone contractsCurrent FAR Rewritten text acquisition.gov Practitioner Album

'Consider socioeconomic programs first' language removed

Removed

Current FAR

Above the SAT the CO shall first consider 8(a), HUBZone, SDVOSB or WOSB before a small business set-aside (FAR 19.203(c)); the CO shall consider HUBZone, SDVOSB and WOSB sole-source awards before a small business set-aside (FAR 19.1306(a), 19.1406(a), 19.1506(a)); for orders above the SAT the same order applies (FAR 19.504(a)(3)).

Rewritten Part 19

FAR 19.203 'Relationship among small business programs' is removed; the small business set-aside is mandatory when the rule of two is met, and it 'does not preclude' awards under the HUBZone, SDVOSB, WOSB or 8(a) programs (RFO 19.104-1(e)). Socioeconomic sole sources become 'may consider' (RFO 19.105-3(a), 19.106-3(a), 19.107-3(a)), and the order-level priority is not carried over (RFO 19.111-2).

What it means for you (our reading)

Socioeconomic set-asides and sole sources remain available, but the FAR no longer tells COs to look at them before an ordinary small business set-aside. Expect more plain small business set-asides where a HUBZone, SDVOSB, WOSB or 8(a) firm might previously have been considered first.

Who it hits: 8(a), HUBZone, SDVOSB, WOSB/EDWOSB firmsCurrent FAR Current FAR Current FAR Current FAR Current FAR Rewritten text Rewritten text Rewritten text Rewritten text acquisition.gov

Size/status rerepresentation on orders

medium confidenceRemoved

Current FAR

Contractors must rerepresent size and socioeconomic status for the NAICS code of certain orders (e.g., a socioeconomic set-aside order under an unrestricted MAC), and the CO may require rerepresentation for any order; agency goal credit follows the order rerepresentation (FAR 19.301-2(b)(2)-(3), (d)(2)).

Rewritten Part 19

Rerepresentation is triggered only by contract-level events: novation, merger or acquisition, and the long-term-contract checkpoints (year five and each later option) (RFO 19.301(a); RFO 52.219-28(b)). Agency credit is driven by the contract-level size status (GSA RFO-2025-19 memo; Practitioner Album).

What it means for you (our reading)

The FAR's own order-level rerepresentation triggers are gone, so fewer orders will ask you to recertify size through the FAR process. SBA's size rules still decide whether you count as small for a particular order, such as a set-aside order under an unrestricted contract (13 CFR 121.404). Check the order's terms before relying on your contract-level status.

Who it hits: Small and recently graduated firms on IDIQs/MACsCurrent FAR Rewritten text Rewritten text acquisition.gov Practitioner Album SBA rule (eCFR)

Limitations on subcontracting

medium confidenceSame Rule, New Words

Current FAR

Part 19 itself states the limits: no more than 50% of the amount paid to non-similarly-situated subcontractors for services and for supplies (excluding materials), 85% for general construction and 75% for special trades, with compliance periods (FAR 19.505(a)-(b)).

Rewritten Part 19

The same percentages and compliance periods now sit in the clause itself (RFO 52.219-14(e)-(f)); Part 19 keeps only the prescription (RFO 19.104-3(c)), with the 8(a) version restated at RFO 19.108-8. The 'similarly situated entity' definition lives only in the clause.

What it means for you (our reading)

The percentages are the same (50/85/75), and they now live in the clause, so read your contract's 52.219-14 (Deviation) text rather than looking for them in Part 19. For 8(a) awards the two texts measure different things: the rewritten Part 19 (19.108-8) looks at the share of personnel or manufacturing costs your own employees perform, while the clause limits what you pay subcontractors that aren't similarly situated. A plan can pass one test and fail the other, so get the contracting officer's answer on which applies before relying on either.

Who it hits: Small primes on set-aside and sole-source workCurrent FAR Rewritten text Rewritten text Rewritten text acquisition.gov

Nonmanufacturer rule

medium confidenceSame Rule, New Words

Current FAR

FAR 19.505(c) lists all nonmanufacturer requirements in Part 19: supply a U.S. small-business-made end item, not exceed 500 employees (150 for IT VARs under 541519), be primarily engaged in retail/wholesale, and take ownership or possession; plus kit, waiver and multiple-item rules.

Rewritten Part 19

RFO 19.104-1(f) keeps the small-business-made end item rule, the kit cap, waivers and the 50% multiple-item test; the 'primarily engaged' and ownership/possession duties move into clause 52.219-33(c); the 500/150-employee cap appears in 52.219-28(d) and SBA's rule (13 CFR 121.406(b)(1)(i)); 'identification of manufacturers' moves to FAR Companion FC 19.104-1(f).

What it means for you (our reading)

Resellers face the same substantive test, but it is now spread across Part 19, two clauses, SBA's regulation and the Companion. Check all of them before relying on a nonmanufacturer strategy.

Who it hits: Small resellers / supply dealersCurrent FAR Rewritten text Rewritten text Rewritten text SBA rule (eCFR) acquisition.gov
Show all 17 changesShow fewer

Partial set-asides of single-award contracts

Narrowed

Current FAR

For contracts other than MACs, the CO 'shall set aside a portion or portions' when a total set-aside isn't appropriate and the listed conditions are met (FAR 19.502-3(a)); partial set-asides of MACs are discretionary (FAR 19.502-4(a)).

Rewritten Part 19

One unified rule says COs 'may, at their discretion' partially set aside any acquisition except construction when the conditions are met (RFO 19.104-2(a)).

What it means for you (our reading)

A big single-award requirement that small firms can only perform in part no longer has to be split to give small businesses a reserved slice. The FAR Council's summary calls the principles identical, but the text moved from 'shall' to 'may'.

Who it hits: Small firms targeting large single-award requirementsCurrent FAR Current FAR Rewritten text acquisition.gov

8(a): compete first below the threshold; sole source above it

New

Current FAR

Below the $5.5M ($8.5M manufacturing) competitive threshold, competitive 8(a) awards need approval from SBA's Associate Administrator for Business Development; above it, SBA may accept a sole source if two 8(a) offers aren't expected or the firm is tribally/ANC-owned (FAR 19.805-1(b), (d)).

Rewritten Part 19

Below the threshold, COs must first try a competitive 8(a) order on SBA-approved government-wide contracts before going sole source (RFO 19.108-7(d)(1)); above it, SBA may accept a sole source only after the CO meets the Part 6 other-than-full-and-open rules (RFO 19.108-7(b); RFO 6.103).

What it means for you (our reading)

Directed 8(a) sole-source awards under the threshold become harder to get where a GWAC with an 8(a) pool exists. 8(a) firms that are not on those vehicles lose ground.

Who it hits: 8(a) participants, especially those relying on sole-source marketingCurrent FAR Rewritten text Rewritten text acquisition.gov Practitioner Album

Release of 8(a) follow-on requirements

New

Current FAR

An 8(a) follow-on stays in the program unless SBA's AA/BD agrees in writing to release it (or a mandatory source applies); release is generally granted when the agency will use a SB, HUBZone, SDVOSB or WOSB set-aside (FAR 19.815(a)-(c)).

Rewritten Part 19

A follow-on is released automatically, with no formal request, if it will be set aside under the HUBZone, SDVOSB or WOSB programs; other releases still need a written request and AA/BD concurrence (RFO 19.108-11(a)-(b)).

What it means for you (our reading)

An incumbent 8(a) firm's work can move to a HUBZone, SDVOSB or WOSB competition without SBA weighing its business-development impact. SBA's own regulation still describes a request-and-concurrence process (see conflicts).

Who it hits: 8(a) incumbents; HUBZone/SDVOSB/WOSB firms gain accessCurrent FAR Rewritten text acquisition.gov acquisition.gov SBA rule (eCFR)

WOSB/EDWOSB: pending applications

medium confidenceNarrowed

Current FAR

An offeror with a pending WOSB/EDWOSB certification application may compete on a WOSB/EDWOSB set-aside; if it is the apparent winner, the CO asks SBA for a determination, which SBA makes within 15 calendar days (FAR 19.1505(d)-(f)).

Rewritten Part 19

For a WOSB/EDWOSB set-aside or sole source, the CO must verify before award that the offeror is designated as certified in SAM; there is no pending-application path in the text (RFO 19.107-1(b); RFO 52.219-29(c), 52.219-30(c)).

What it means for you (our reading)

In agencies using the deviation, women-owned firms should hold an actual certification before bidding on WOSB/EDWOSB set-asides. SBA's rule still allows pending applicants (see conflicts), so expect disputes.

Who it hits: Women-owned firms awaiting SBA or third-party certificationCurrent FAR Rewritten text Rewritten text Rewritten text SBA rule (eCFR)

SDVOSB: certification transition language dropped

Narrowed

Current FAR

An SDVOSB qualifies if it is SBA-certified in SAM or self-represented in SAM and applied to SBA on or before December 31, 2023 (FAR 19.1403(b), 19.1405(c), 19.1406(b)).

Rewritten Part 19

The CO verifies that the offeror is designated in SAM as an SBA-certified SDVOSB; the 2023 grandfather path is gone (RFO 19.106-1(b); RFO 52.219-27(c)). DoD's Revision 1 deviation uses alternate verification procedures at DFARS 219.106-70 until SAM.gov aligns with the FAR.

What it means for you (our reading)

Only SBA-certified SDVOSBs (VetCert) count. Few firms should still be pending from 2023, but any that are are now out.

Who it hits: SDVOSBsCurrent FAR Current FAR Rewritten text Rewritten text DoD deviation

Counting subcontractors toward prime goals

medium confidenceNarrowed

Current FAR

To count under a subcontracting plan, a subcontractor may represent itself as small, VOSB, SDVOSB, HUBZone, SDB or WOSB, and the prime may accept the representation (FAR 19.703(a)).

Rewritten Part 19

A subcontractor represents itself only as small or SDB; for VOSB, SDVOSB, HUBZone or WOSB it must be certified by SBA (RFO 19.302-2(a)(1)).

What it means for you (our reading)

Large primes may stop counting self-certified veteran-owned or woman-owned subs toward socioeconomic goals and favor certified firms. SBA's current rule only bars self-certification for HUBZone and SDVOSB subcontractors, so the scope is contested.

Who it hits: Small subcontractors to large primes (VOSB, WOSB especially)Current FAR Rewritten text SBA rule (eCFR)

Subcontracting reports: eSRS to SAM.gov SPR, 45 days

Narrowed

Current FAR

ISRs and SSRs go into eSRS; reports are due 30 days after each period ends, and COs must acknowledge or reject them within 60 days (FAR 19.704(a)(10)(iv), 19.705-6(f), (j)).

Rewritten Part 19

Reports go into Subcontracting Plan Reporting (SPR) at SAM.gov within 45 days after the period ends (e.g., by Nov 14 for the FY ending Sept 30); CO acknowledge/reject steps are removed and agencies set their own monitoring (RFO 19.302-2(a), 19.302-3(f), 19.206-1(c)(4)); this came from the February 20, 2026 supplement.

What it means for you (our reading)

Reports move to a new system, SPR at SAM.gov. The February 20, 2026 update set 45 days, but the codified FAR and the earlier deviation clause say 30, and an awarded contract changes only when it is modified. Read the deadline in your contract's own 52.219-9 text, and use 45 days only if that text or your contracting officer says 45.

Who it hits: Other-than-small primes with subcontracting plans; small firms that grew out of sizeCurrent FAR Current FAR Rewritten text Rewritten text Practitioner Album acquisition.gov

Small business specialist / PCR review role

medium confidenceRemoved

Current FAR

The contracting activity must coordinate with the agency small business specialist no later than 30 days before issuing a solicitation (FAR 19.201(d)(1)); FAR 19.201(c) lists OSDBU duties; PCRs may review any proposed acquisition above the MPT on request (FAR 19.501(d)) and may pick acquisitions for review at their discretion (FAR 19.202-1(e)(1)(iv)).

Rewritten Part 19

RFO 19.102 keeps the 30-day package to the PCR for bundled, consolidated or too-large requirements, the 15-day PCR recommendation, the rejection/appeal chain and the OSDBU recommendation review (RFO 19.102(e)-(g)). The specialist 30-day coordination, the OSDBU duty list, the any-acquisition review and the discretionary-review trigger are not in RFO Part 19; the specialist appears only in subcontracting-plan review (RFO 19.206-3(d)(7)) and bundling plans (RFO 7).

What it means for you (our reading)

There are fewer built-in checkpoints where an advocate must see a requirement before release. Small firms should take capability briefings to the OSDBU and PCR early instead of counting on a mandatory review.

Who it hits: All small businesses relying on SB advocates in market researchCurrent FAR Current FAR Current FAR Rewritten text Rewritten text Practitioner Album

Reserves: direct orders to a sole reserve awardee

Removed

Current FAR

Under a MAC reserve, if there is only one award to a given type of small business, the CO may issue orders directly to it (FAR 19.504(c)(1)(ii)); clause 52.219-32 implements this (FAR 19.507(g)(2)).

Rewritten Part 19

Reserves remain discretionary (RFO 19.112), but clause 52.219-32 is removed and there is no direct-order authority; orders under reserves follow the general order set-aside rule (RFO 19.111-2; RFO 52.219-32 [Reserved]).

What it means for you (our reading)

Holding the only reserve slot no longer guarantees a path to orders. Reserve awardees must compete for set-aside or unrestricted orders.

Who it hits: Small businesses holding reserve awards on full-and-open MACsCurrent FAR Current FAR Rewritten text Rewritten text acquisition.gov

Certificate of Competency: agency appeal path

medium confidenceRemoved

Current FAR

For COCs between $100,000 and $25 million, an agency can appeal SBA's intent to issue a COC to SBA headquarters through its OSDBU; above $25 million SBA HQ offers the agency a review (FAR 19.602-3).

Rewritten Part 19

FAR 19.602-3 is removed; RFO 19.204 keeps mandatory referral, the 15-business-day hold, and says SBA COCs are final on all elements of responsibility (RFO 19.204(f), (i)).

What it means for you (our reading)

In the FAR text, an SBA COC is no longer second-guessed through an agency appeal. Whether SBA's own COC regulation keeps an agency appeal was not checked (see gaps).

Who it hits: Small businesses found nonresponsibleCurrent FAR Rewritten text acquisition.gov

HUBZone 10% price evaluation preference mechanics

Moved to Guidance

Current FAR

The 10% factor shall be applied by line item or group of items, other factors are added first, and a tie between a HUBZone firm and a large business goes to the HUBZone firm (FAR 19.1307(c)-(d)).

Rewritten Part 19

The 10% preference itself stays mandatory in full and open competition (RFO 19.110, 19.207); the line-item method and tie-break move to the FAR Companion as 'should' guidance (FC 19.110).

What it means for you (our reading)

HUBZone firms keep the preference, but the tie-break and line-item mechanics are no longer binding regulation. Ask the CO how the factor will be applied.

Who it hits: HUBZone firms in full-and-open competitionsCurrent FAR Rewritten text Rewritten text acquisition.gov Practitioner Album

What did not change

Worth knowing before you rework anything.

Size standards, NAICS assignment and the October 1, 2028 multi-NAICS MAC date

Same rules: one NAICS code per solicitation; for MAC solicitations issued after October 1, 2028, either one NAICS or one per distinct portion/category; size is set as of the initial offer with price; NAICS appeals are due within 10 calendar days.

Current FAR

Sole-source and 8(a) competitive dollar thresholds

HUBZone and WOSB/EDWOSB sole sources: $5.5M ($8.5M manufacturing); SDVOSB: $5M ($8.5M manufacturing); 8(a) competitive threshold $5.5M ($8.5M manufacturing); 8(a) sole sources over $30M still need a justification.

Current FAR

Subcontracting plan threshold, good-faith test and liquidated damages

Plans are still required above $900,000 ($2 million construction) when subcontracting possibilities exist; plans are not required from small businesses; missing goals alone is not bad faith; liquidated damages equal the shortfall.

Current FAR

Size protest mechanics

Interested parties still have 5 business days after notice of the apparent awardee; SBA Area Offices decide within 15 business days; award is held unless the CO determines otherwise in writing.

Current FAR

Limitations-on-subcontracting percentages

50% services, 50% supplies (excluding materials), 85% general construction, 75% special trades; similarly situated subs still count as self-performance.

Current FAR

What to do now

  1. 1List your multiple-award contracts (MAS, GWACs, agency IDIQs) and check each one's order set-aside clause: the mandatory version, or modified to the rewritten clause? Where the rewritten clause applies, plan your pipeline assuming order set-asides are discretionary and not protestable.See the change
  2. 2If you are a WOSB/EDWOSB with a pending application, finish SBA or third-party certification and confirm it shows in SAM before bidding WOSB set-asides at deviation agencies.See the change
  3. 3If you subcontract to large primes as a veteran-owned or woman-owned firm, get SBA certification (VetCert or WOSB) so the prime can count you toward its socioeconomic goals.See the change
  4. 4If you hold a socioeconomic certification, brief OSDBU and SBA PCRs during market research and ask for a HUBZone, SDVOSB, WOSB or 8(a) set-aside in writing, because the FAR no longer tells COs to consider those programs first.See the change
  5. 58(a) firms: get on SBA-approved government-wide vehicles that allow 8(a) order competition, since below-threshold work must be tried there before a sole source.See the change
  6. 6If you hold a subcontracting plan, read the reporting deadline in your contract's own 52.219-9 text before the next report is due. File in SPR at SAM.gov, and use 45 days only if that text or your contracting officer says 45; otherwise keep to 30.See the change

Agency adoption dates for Part 19

Dates read from each agency's Part 19 class deviation. "Basis" says which date the memo gives.

Part 19 class deviation dates by agency
AgencyDateBasisSource
Commodity Futures Trading CommissionNov 3, 2025effectiveMemo
Department of Homeland SecurityNov 3, 2025effectiveMemo
Department of Housing and Urban DevelopmentNov 3, 2025effectiveMemo
Department of LaborNov 3, 2025effectiveMemo
General Services AdministrationNov 3, 2025effectiveMemo
U.S. Department of AgricultureNov 3, 2025effectiveMemo
Consumer Product Safety CommissionNov 13, 2025signatureMemo
Department of TransportationNov 14, 2025signatureMemo
Millennium Challenge CorporationNov 14, 2025effectiveMemo
Department of Veterans AffairsNov 19, 2025signatureMemo
Udall FoundationNov 24, 2025signatureMemo
Department of the TreasuryNov 25, 2025signatureMemo
National Science FoundationDec 2, 2025first date in memoMemo
Department of EnergyDec 8, 2025signatureMemo
Department of JusticeDec 8, 2025signatureMemo
Nuclear Regulatory CommissionDec 11, 2025signatureMemo
Department of EducationDec 12, 2025signatureMemo
Department of CommerceJan 15, 2026effectiveMemo
National Archives and Records AdministrationJan 26, 2026first date in memoMemo
Department of the InteriorJan 30, 2026effectiveMemo
Department of DefenseFeb 1, 2026effectiveMemo
Environmental Protection AgencyFeb 9, 2026signatureMemo
National Aeronautics and Space AdministrationFeb 20, 2026signatureMemo
Pension Benefit Guaranty CorporationFeb 23, 2026signatureMemo
Securities and Exchange CommissionFeb 25, 2026signatureMemo
Department of StateFeb 27, 2026effectiveMemo
Office of Personnel ManagementApr 29, 2026signatureMemo
Consumer Financial Protection BureauJun 8, 2026signatureMemo
Federal Communications CommissionAug 6, 2026effectiveMemo

Part 19 questions, answered

Are order set-asides still required under the new FAR Part 19?+

Not where the rewrite applies. Under the model text, setting aside an order on a multiple-award contract is up to the contracting officer, and that choice is not a basis for protest. An awarded contract keeps the clauses it has until it is modified, so check yours. The rule of two still applies to standalone contracts.

Does the rule of two still apply to small business contracts?+

Yes. For contracts above the micro-purchase threshold, the CO must set the contract aside when two or more responsible small businesses are expected to make competitive offers, and must document a decision not to. The FAR Council kept this above the SAT even though only the band below the SAT is statutory.

Do I still have to rerepresent my size for task orders?+

The FAR's order-level triggers are gone in the model text: rerepresentation follows contract-level events (a novation, a merger or acquisition, and the long-term-contract checkpoints at year five and each later option). SBA's size rules still apply to some orders, such as set-aside orders under unrestricted contracts, so read each order's terms.

Did the limitations on subcontracting change in the FAR overhaul?+

The percentages did not: 50% for services and supplies, 85% for general construction and 75% for special trades. They moved out of Part 19 and into the 52.219-14 clause, so read the clause in your contract. For 8(a) awards, the rewritten Part 19 measures your own employees' share of costs while the clause limits payments to subcontractors that aren't similarly situated. Ask the contracting officer which applies before relying on either.

Can a women-owned business with a pending WOSB certification still bid on WOSB set-asides?+

The current codified FAR and SBA's rule allow it, but the RFO model text requires the CO to verify the firm is certified in SAM before award, with no pending-application path. If you are pursuing WOSB or EDWOSB set-asides at an agency using the deviation, get certified first.

Is the new FAR Part 19 actually in effect?+

It is in effect agency by agency through class deviations. For example, GSA's took effect November 3, 2025 and DoD's February 1, 2026. It is not yet codified: as of November 2, 2026, no proposed rule for Part 19 appears in the Federal Register.

What happened to eSRS subcontracting reports?+

Under the February 20, 2026 update to the model text, reports go to Subcontracting Plan Reporting (SPR) in SAM.gov, and the updated clause allows 45 days after each period instead of 30. The codified FAR and the earlier deviation clause still say 30, so go by the deadline written in your contract's own clause or your contracting officer's direction.

Sources and method

Each change compares the current FAR Part 19 with the FAR Council's rewritten model text, read on Nov 2, 2026. "What it means for you" is Honest Echo's reading, not regulatory text or legal advice. Changes marked medium confidence rest on what the rewrite leaves out, or on an SBA rule we could not fully reconcile; check the sources before relying on them. The status line at the top updates weekly with the tracker.

  • Current FAR Part 19
  • Rewritten Part 19 (model deviation text)
  • Part 19 Practitioner Album
  • DoD class deviation 2026-O0037

More guides

All guides
FAR overhaul

FAR 2.0 cheat sheets: printable references

Read the guide
FAR overhaul

FAR Overhaul Tracker (FAR 2.0)

Read the guide
Sources Sought

Should you respond to that Sources Sought notice?

Read the guide
SAM.gov search

The SAM.gov opportunities its own search hides

Read the guide
Recompetes

See the recompete coming before the RFP does

Read the guide

Get FAR 2.0 changes every Monday

A free Monday email with what changed in the FAR overhaul that week, which agencies adopted which parts, and what’s coming next. It’s built from the same weekly check of acquisition.gov, the Federal Register and DoD’s deviation list as this tracker.

We’ll save your picks with your signup: FAR Part 19.

We’ll email you a link to confirm your address before your Monday emails begin. You can unsubscribe anytime, and we never sell your address.

Will Part 19's rewrite change your next bid?

Check the notice before you commit. Paste a SAM.gov notice and get a fit score and a bid/no-bid read in minutes.

Analyze a notice, free Back to the tracker